Case Studies
Major Project Summary
Bankside
58 Panel Areva WBD double busbar 11KV switchgear, installation and commissioning, 28 Panel 22KV Areva WS double busbar switchboard commissioning for an EDF project at Tate Modern central London.

Bankside 22KV WS
Basildon Grid
132KV to 33kV Grid site, full commissioning of 2 x 90MVA grid transformers and associated protection including 33kV Rough balance scheme and 132kV intertrip scheme.
Earlham Grid
132KV to 33kV Grid site, full commissioning of 2 x 90MVA grid transformers and associated protection including 33kV Rough balance scheme and 132kV intertrip scheme.
Peterborough East
132KV to 11kV Grid site, full commissioning of grid transformers and associated protection including integrating into existing 11kV circuits and 132kV intertrip scheme.
Thorpe Grid
132KV to 11kV Grid green field site, full commissioning of the site, grid transformers, 11kV switchboard and associated protection including differential relays with fibre optic connection and 132kV intertrip scheme.
CTRL
Commissioning and protection modifications of over 30 substations of Hawkvac 15 11KV Switchgear for the new Channel Tunnel Rail Link from St Pancras Station to Ebbsfleet International Station in Kent.
Canary Wharf
Installation and commissioning of Eclipse 11KV switchboards at Morgan Stanley and Lehman Brothers. Carry out Site Integration Testing, commissioning and fault finding at some of the most high profile buildings in the country at Canary Wharf, also Swiss RE (i.e. 'The Gerkin').

Eclipse Switchboard
British Gas Offshore Rig
Carrying out protection modifications and commissioning.
Norwich Union
Commissioning of 6 x 11kV Switchboards for new data centre, including generator switchboards and final commissioning of G59 generator protection.
Hameldon Hill Windfarm
Drawing approval, design modifications, relay software modifications, commissioning of the site including G59 testing witnessed and approved by the local electricity board.
HSBC Data Centre
Installation and commissioning of 4 11KV switchboards at HSBC Data Centre, Welwyn Garden City.
Greater Gabbard Offshore Windfarm
Cold commissioning, on behalf of Areva, of 3 Panel Areva WS 33KV Switchgear in each windturbine. There are 140 3.75MW wind turbines in total on this offshore windfarm off the coast of Ipswich. Commissioning was carried out in Vlissingen, Holland before being shipped across to the UK.
The Shard
Install and commission Areva Visax switchboard in the largest building in Europe.
Huntingdon Grid
132KV to 11kV Grid site, full commissioning of grid transformers and associated protection including integrating into new Eaton Holec 11kV switchboard and 132kV intertrip scheme on behalf of Carillion for UK Power Networks.
Heathrow
Commission 2 x 10 Panel 33KV WS switchboard at Heathrow on behalf of Areva for UK Power Networks.